Concrete Calculator

Concrete volume, cement bags, sand and aggregate

What are you pouring?

%

Concrete Needed

2.63 m³Concrete volume
22Cement (50 kg bags)
92.7 cftIn cubic feet
1.1 m³ (38.9 cft)
Sand
2.21 m³ (77.9 cft)
Aggregate (20 mm)
1,058 kg
Cement weight
3.43
Cubic yards

Working

  1. Wet volume = 2.5 m³ × 1 + 5% wastage = 2.625 m³
  2. Dry volume = 2.625 × 1.54 = 4.043 m³
  3. Mix 1 : 1.5 : 3 (5.5 parts): cement = 4.043 × 1/5.5 = 0.735 m³ ÷ 0.0347 = 21.2 bags
  1. 1
    Choose the shape
    Slab, footing, beam or column
  2. 2
    Enter the size
    In metres, feet, mm or inches
  3. 3
    Get the materials
    Volume, cement bags, sand, aggregate

How is concrete quantity calculated?

Work out the wet volume, convert to dry volume (materials bulk up and shrink when mixed), then split it by the mix ratio:

Wet volume = length × width × thickness

Dry volume = wet volume × 1.54

Cement = dry volume × cement share ÷ 0.0347 m³ per bag

1 m³ = 35.31 cft

Which grade to use

M20 is the usual minimum for RCC slabs, beams and columns in homes. M10 and M15 are for plain concrete (PCC) such as levelling beds under footings and floors. For big or high-rise work, use a design mix from a structural engineer.

Ready-mix concrete

For volumes over about 3 m³, ready-mix (RMC) is often more consistent and less work. Order the wet volume in m³ plus 5–10% extra.

Related calculators

Frequently asked questions

How many cement bags are needed for 1 m³ of M20 concrete?

About 8 bags (50 kg each), with roughly 15 cft of sand and 30 cft of 20 mm aggregate.

Why multiply by 1.54?

Dry cement, sand and aggregate have air gaps that fill up when mixed with water, so you need about 54% more dry material than the finished wet volume.

How thick should a house roof slab be?

Commonly 125–150 mm (5–6 inches) for residential RCC slabs, but always follow your structural drawings.

How much cement is needed for a 1,000 sq ft slab?

A 5-inch (125 mm) M20 slab of 1,000 sq ft takes about 11.8 m³ of concrete, or roughly 95 bags of cement, plus 5–10% extra for wastage.

Sources

Last reviewed: October 2026